SURYA TOWER-IIIMahaRERA P50600011213

by BIRENDRA KAMDEO SINGH

PLOT NO.1, Bhandara (M Cl), 441904

Jan 2020
Possession
61.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jan 2020) has passed with construction at 61.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2020 per the RERA filing.

Official RERA facts

Registration
P50600011213
Status
Ongoing
Stage
Certificate Signed
Possession
January 2020originally January 2019
Construction
61.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths45%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)25%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lighting75%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parking40%

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of SURYA TOWER-III โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SURYA TOWER-III. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.