J. K. HEIGHTSMahaRERA P50600023850

by SKY DEVELOPERS AND PROMOTERS INDIA PVT. LTD.

1943,42,16/171,1943,42,16/172, SARAFA BAZAAR, 441912

Dec 2026
Possession
65.5%
Built
0
Complaints
79
Units
Caution
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P50600023850
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
65.5% complete
Units sold
28 of 79

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply65%
Water conservation /Rain water harvestingnot started

Building & registration

RERA registered
Jan 2020
Floors
6
Unit mix
14 res ยท 65 comm
Architect
Vishwash Gupta

Buyer community

Connect with other buyers and owners of J. K. HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching J. K. HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.