PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SAI SHOPPING COMPLEXMahaRERA P51000013171

by SAI DEVELOPERS

3,4/73,76.2, Ghatanji, 445301

Aug 2020
Possession
81.8%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Aug 2020) has passed with construction at 81.8%.
Ghatkopar / VikhroliUpper-mid

Metro-1 anchor with Godrej's Vikhroli land bank next door.

Growth drivers:
Metro 1 interchange, Eastern Express Highway, corporate campuses.
Who buys here:
Families wanting east-side connectivity to BKC/Fort.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51000013171
Status
Ongoing
Stage
Certificate Signed
Possession
August 2020
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Water conservation /Rain water harvesting50%
Open Parkingdone

Building & registration

RERA registered
Sept 2017
Floors
3

Buyer community

Connect with other buyers and owners of SAI SHOPPING COMPLEX โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI SHOPPING COMPLEX. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.