GVC SHAGUN CITY IVMahaRERA P51100047816

by SHAGUN BUILDCON

GUT NO 174 S NO 50, KAUTHA, 431603

Dec 2025
Possession
70.6%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 70.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.

Official RERA facts

Registration
P51100047816
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
70.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drains30%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildings50%
Aggregate area of recreational Open Space30%

Building & registration

RERA registered
Nov 2022
Floors
3

Buyer community

Connect with other buyers and owners of GVC SHAGUN CITY IV โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GVC SHAGUN CITY IV. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.