Mangalmurti ResidencyMahaRERA P51300048942

by MAHESH BALKISHAN SONI

Plot No. 5,6,7,8,9,10,11 and 12, SY No. 25, Gt No 81, Ward No. 19, Parbhani, 431401

Nov 2027
Possession
50.9%
Built
0
Complaints
60
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Nov 2025, now proposed Nov 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2027 per the RERA filing.

Official RERA facts

Registration
P51300048942
Status
New
Stage
Certificate Signed
Possession
November 2027originally November 2025
Construction
50.9% complete
Units sold
32 of 60

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvesting10%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jan 2023
Floors
6
Unit mix
50 res ยท 10 comm
Architect
Rahul S. Gangwal

Buyer community

Connect with other buyers and owners of Mangalmurti Residency โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Mangalmurti Residency. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.