SHREE SAI CITY PHASE-IMahaRERA P51400008469

by SHREE SAI CITY BUILDERS AND DEVELOPERS

S NO 63, JALNA, 431203

Jun 2027
Possession
63.4%
Built
0
Complaints
247
Units
High risk
  • Possession delayed ~7 yrs. Originally promised Sept 2020, now proposed Jun 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P51400008469
Status
Ongoing
Stage
Certificate Signed
Possession
June 2027originally September 2020
Construction
63.4% complete
Units sold
157 of 247

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Landscaping & Tree Planting50%
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvesting50%
Energy managemcnt50%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Space50%
Open Parking50%

Building & registration

RERA registered
Aug 2017
Floors
480
Unit mix
223 res ยท 24 comm

Buyer community

Connect with other buyers and owners of SHREE SAI CITY PHASE-I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHREE SAI CITY PHASE-I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.