Under construction

Ramchintan ParkMahaRERA P51500006207

by Mewani Infrstrcture

Gut No 13 P Plot No 42, Aurangabad, 431003

Oct 2026
Possession
53.8%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Sept 2022, now proposed Oct 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2026 per the RERA filing.

Official RERA facts

Registration
P51500006207
Status
Ongoing
Stage
Certificate Signed
Possession
October 2026originally September 2022
Construction
53.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Landscaping & Tree Plantingnot started
Street Lighting50%
Water conservation /Rain water harvesting50%
Aggregate area of recreational Open Spacenot started
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of Ramchintan Park โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Ramchintan Park. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.