Under construction

kalyani classicMahaRERA P51500006528

by Bhagwan pandurang Ghadge

19048/1/ 59,62, Aurangabad (M Corp.), 431010

Apr 2018
Possession
63.6%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Apr 2018) has passed with construction at 63.6%.

Official RERA facts

Registration
P51500006528
Status
Ongoing
Stage
Certificate Signed
Possession
April 2018
Construction
63.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parking80%

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of kalyani classic โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching kalyani classic. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.