All RERA projects
๐๏ธ
Under construction
BIZ SQUAREMahaRERA P51500008228
by SAM REALTIES
PLOT NO 8,9,13 TO 16, Gut No 58, 431005
Apr 2025
Possession
73.2%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~5 yrs. Originally promised Dec 2019, now proposed Apr 2025 per the RERA filing.
- Possession date passed. The proposed possession date (Apr 2025) has passed with construction at 73.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2025 per the RERA filing.
Official RERA facts
- Registration
- P51500008228
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- April 2025originally December 2019
- Construction
- 73.2% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station30%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 5
Buyer community
Connect with other buyers and owners of BIZ SQUARE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching BIZ SQUARE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.