BIZ SQUAREMahaRERA P51500008228

by SAM REALTIES

PLOT NO 8,9,13 TO 16, Gut No 58, 431005

Apr 2025
Possession
73.2%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Dec 2019, now proposed Apr 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Apr 2025) has passed with construction at 73.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2025 per the RERA filing.

Official RERA facts

Registration
P51500008228
Status
Ongoing
Stage
Certificate Signed
Possession
April 2025originally December 2019
Construction
73.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station30%

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of BIZ SQUARE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BIZ SQUARE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.