All RERA projects
๐๏ธ
Under construction
VENKATESH VISHWAMahaRERA P51500011725
by TIRUPATI BUILDERS AND DEVELOPERS
PLOT NO 30,31,32,33 GUT NO 32/2, AURANGABAD, 431007
Mar 2022
Possession
50.9%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~3 yrs. Originally promised Mar 2019, now proposed Mar 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 50.9%.
Official RERA facts
- Registration
- P51500011725
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2022originally March 2019
- Construction
- 50.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply50%
Water conservation /Rain water harvestingnot started
Open Parking50%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 5
Buyer community
Connect with other buyers and owners of VENKATESH VISHWA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching VENKATESH VISHWA. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.