MSQUARE HEIGHTSMahaRERA P51500014491
GUT NO. 269, Aurangabad (M Corp.), 431001
Dec 2028
Possession
31.8%
Built
0
Complaints
19
Units
High risk
- Possession delayed ~5 yrs. Originally promised Oct 2023, now proposed Dec 2028 per the RERA filing.
Official RERA facts
- Registration
- P51500014491
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2028originally October 2023
- Construction
- 31.8% complete
- Units sold
- 2 of 19
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station1%
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Dec 2017
- Floors
- 10
- Unit mix
- 13 res · 6 comm
- Architect
- MD HARES SIDDHIQUI
Buyer community
Connect with other buyers and owners of MSQUARE HEIGHTS — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet — start one and connect with the next buyer researching MSQUARE HEIGHTS. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities — what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.