KISAN PARKMahaRERA P51500018345
G NO 80, NEAR DISHA NIWARA, PISADEVI, 431008
Dec 2026
Possession
20.1%
Built
0
Complaints
116
Units
High risk
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.
- Behind schedule. Possession is due Dec 2026 but construction is only at 20.1%.
Official RERA facts
- Registration
- P51500018345
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2024
- Construction
- 20.1% complete
- Units sold
- 67 of 116
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply95%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsnot started
Landscaping & Tree Plantingdone
Street Lighting90%
Water conservation /Rain water harvesting45%
Electrical meter room, sub-station, receiving station35%
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Oct 2018
- Floors
- 6
- Unit mix
- 110 res ยท 6 comm
- Architect
- DHANANJAY B DOIFODE
Buyer community
Connect with other buyers and owners of KISAN PARK โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching KISAN PARK. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.