NARAYANA RESIDENCYMahaRERA P51500022026

by SHRI NARAYANA BUILDERS

GUT NO.34P, PLOT NO.37,40 AND 41, HIRAPUR, 431001

Jun 2022
Possession
84.5%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 84.5%.

Official RERA facts

Registration
P51500022026
Status
New
Stage
Certificate Signed
Possession
June 2022
Construction
84.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started

Building & registration

RERA registered
Aug 2019
Floors
5

Buyer community

Connect with other buyers and owners of NARAYANA RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NARAYANA RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.