GREEN WOODSMahaRERA P51500022372

by CHINTAMANI INFRASTRUCTURE

GUT NO 15 PART, GOLWADI, 431005

Dec 2027
Possession
28.5%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Mar 2025, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51500022372
Status
New
Stage
Certificate Signed
Possession
December 2027originally March 2025
Construction
28.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply35%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2019
Floors
8

Buyer community

Connect with other buyers and owners of GREEN WOODS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GREEN WOODS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.