ELEMENTS ARIAMahaRERA P51500032743

by PADMANABH BUILDERS

SURVEY NO 19 PART SHAHNOORWADI AURANGABAD, SHAHNOORWADI, 431005

Dec 2027
Possession
72.3%
Built
0
Complaints
22
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51500032743
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2025
Construction
72.3% complete
Units sold
7 of 22

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths40%
Water Supply60%
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Landscaping & Tree Plantingnot started
Street Lighting30%
Water conservation /Rain water harvesting40%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jan 2022
Floors
9
Unit mix
22 res ยท 0 comm
Architect
SAMIL ARCHITECTS

Buyer community

Connect with other buyers and owners of ELEMENTS ARIA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ELEMENTS ARIA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.