Under construction

KANHERE RESIDENCYMahaRERA P51500033378

by SHESHNARAYAN VILAS KANHERE

PLOT NO 8, SURVEY NO 23 PART, CIDCO, AURANGABAD, 431001

Jan 2024
Possession
48.2%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jan 2024) has passed with construction at 48.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2024 per the RERA filing.

Official RERA facts

Registration
P51500033378
Status
New
Stage
Certificate Signed
Possession
January 2024
Construction
48.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply20%
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting20%
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Feb 2022
Floors
6

Buyer community

Connect with other buyers and owners of KANHERE RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KANHERE RESIDENCY. Real notes from real buyers beat any brochure.