Under construction

ATHARVA PARK PHASE - IMahaRERA P51500045300

by SHIVSAI CONTRACTORS

Gut No. 108, Devlai, Aurangabad, Aurangabad, 431001

Mar 2027
Possession
56.3%
Built
0
Complaints
32
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51500045300
Status
New
Stage
Certificate Signed
Possession
March 2027originally March 2026
Construction
56.3% complete
Units sold
28 of 32

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Water conservation /Rain water harvesting95%
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
May 2022
Floors
3
Unit mix
32 res ยท 0 comm
Architect
Dhananjay Doifode Doifode

Buyer community

Connect with other buyers and owners of ATHARVA PARK PHASE - I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ATHARVA PARK PHASE - I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.