Under construction

Swastik TowersMahaRERA P51500047135

by Hari Om Developers

Plot nos. 11 to 16, Gut No 4 Part,, Pisadevi, Aurangabad, 431010

Aug 2027
Possession
77.4%
Built
1
Complaints
48
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Aug 2025, now proposed Aug 2027 per the RERA filing.

Official RERA facts

Registration
P51500047135
Status
New
Stage
Certificate Signed
Possession
August 2027originally August 2025
Construction
77.4% complete
Units sold
16 of 48

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station80%

Building & registration

RERA registered
Oct 2022
Floors
5
Unit mix
48 res ยท 0 comm
Architect
Dhananjay B Doifode

Buyer community

Connect with other buyers and owners of Swastik Towers โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Swastik Towers. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.