KRUSHNA ULTIMAMahaRERA P51500053860
Plot Nos- 301, 302, 303(Amalgamated), Gut No- 1/1 (Part), Sundarwadi, 431001
- Possession delayed ~3 yrs. Originally promised Feb 2025, now proposed Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P51500053860
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally February 2025
- Construction
- 9.1% complete
- Units sold
- 8 of 24
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Possession extension history
- EA12062621337Revised to December 2027
We, Prachiti Developers, the promoter of the project “Krushna Ultima” (Registration No. P51500053860) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apologize for the delay in the completion of the project and the submission of this request. We would like to state that the project is approximately 80–90% completed and only minor work remains pending. Therefore, we are now focusing on the marketing and sale of the project units. We require additional time to effectively market and sell the units in the project. Our sales team is actively working on the same and making every possible effort to generate sales. Considering the above circumstances, we kindly request an extension until 31-12-2027 to complete the remaining work and fulfil all regulatory requirements.
Building & registration
- RERA registered
- Dec 2023
- Floors
- 3
- Unit mix
- 24 res · 0 comm
- Plot / CTS / survey no.
- Plot Nos- 301, 302, 303(Amalgamated), Gut No- 1/1 (Part)
- Planning authority
- City and Industrial Development Corporation of Maharashtra Limited
- Approved layout land
- 1,346.19 sq.m
- Land for this registration
- 1,346.19 sq.m
- Permissible built-up area
- 2,196.44 sq.m
- Registered office
- SHOPPING COMPLEX
- North
- Plot No 300
- South
- 24 Mtr Road
- East
- Gut No 01 01 Part
- West
- 9 Mtr Road
Project bank account
The RERA-designated account this project's payments should go to — verify before wiring any money.
- YES BANK — 169397IFSC YESB0LNSB05A-13, N-11, Sudarshan Nagar, TV Center Road, Hudco, Aurangabad- 431003
Commencement Certificate documents
- cidco.pdf
Buyer community
Connect with other buyers and owners of KRUSHNA ULTIMA — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet — start one and connect with the next buyer researching KRUSHNA ULTIMA. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.