PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Aakash Ganga Phase IIMahaRERA P51500054973

by Aakash Ganga Developers

Gut NO 20(P), Mouje-Nakshtrawadi, 431005

Feb 2027
Possession
63.6%
Built
0
Complaints
12
Units
Caution
  • Possession delayed ~1 yr. Originally promised Oct 2025, now proposed Feb 2027 per the RERA filing.

Official RERA facts

Registration
P51500054973
Status
New
Stage
Certificate Signed
Possession
February 2027originally October 2025
Construction
63.6% complete
Units sold
7 of 12

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Possession extension history

  • EA08092502533Revised to February 2027

    We have encountered unforeseen delays in the completion of the project, primarily due to a difference between the demand we had initially anticipated during the registration process and the actual market response observed after commencement. At the time of registration, the original project timeline was based on our comprehensive assessment of expected demand. However, as the project progressed, it became clear that the market response was not aligned with our initial projections. This variance in demand has led to several adjustments in our construction schedule, resulting in a revised and extended completion timeline. Given the unexpected nature of these market fluctuations and the necessary adjustments to our planning

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply99%
Sewerage (Chamber, Lines, Septic Tank , STP)99%
Landscaping & Tree Planting99%
Street Lighting99%
Open Parkingnot started

Building & registration

RERA registered
Feb 2024
Floors
2
Unit mix
12 res ยท 0 comm
Architect
SATYAM B JADHAV
Plot / CTS / survey no.
Gut NO 20(P)
Planning authority
Municipal Corporation Chhtrapati Sambhajinagar
Approved layout land
3,712 sq.m
Land for this registration
3,712 sq.m
Permissible built-up area
929.76 sq.m
Registered office
Veer Shanti
Plot boundaries
North
Part of land bearing Gut No 17
South
Part of land bearing Gut No20
East
Pathway and row house block D
West
Row House Block B
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • SARASWAT COOPERATIVE BANK LIMITED โ€” 143185
    IFSC SRCB0000090
    Kanchan Chambers , Kranti chowk Station Road

Commencement Certificate documents

  • Commencement Certificate.pdf
  • Mail Reply.pdf

Buyer community

Connect with other buyers and owners of Aakash Ganga Phase II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Aakash Ganga Phase II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.