Under construction

Nayantara Presidency Phase 4MahaRERA P51600000098

by Pancharatna Builcon Pvt. Ltd

881/1A/1, Rajiv nagar, 422002

Mar 2028
Possession
69.5%
Built
1
Complaints
112
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Mar 2024, now proposed Mar 2028 per the RERA filing.

Official RERA facts

Registration
P51600000098
Status
Ongoing
Stage
Certificate Signed
Possession
March 2028originally March 2024
Construction
69.5% complete
Units sold
9 of 112

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths20%
Water Supply10%
Sewerage (Chamber, Lines, Septic Tank , STP)10%
Storm Water Drains50%
Landscaping & Tree Planting50%
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2017
Floors
16
Unit mix
112 res ยท 0 comm
Architect
Dinesh Bhamre

Buyer community

Connect with other buyers and owners of Nayantara Presidency Phase 4 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Nayantara Presidency Phase 4. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.