Dec 2021
Possession
85.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 85.9%.

Official RERA facts

Registration
P51600001608
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021originally December 2019
Construction
85.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting80%
Street Lighting60%
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirements95%
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone
Security Cabindone

Building & registration

RERA registered
Jul 2017
Floors
14

Buyer community

Connect with other buyers and owners of Madhoor Maitri โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Madhoor Maitri. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.