Under construction

United Courtyard Phase IMahaRERA P51600001925

by United Builders

Plot no 11 Sr No 20/2/1-2 Village Taluka and District Nashik, BEHIND INOX, 422006

Sept 2020
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 90.9%.

Official RERA facts

Registration
P51600001925
Status
Ongoing
Stage
Certificate Signed
Possession
September 2020originally March 2019
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Community Buildingsdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Jul 2017
Floors
8

Buyer community

Connect with other buyers and owners of United Courtyard Phase I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching United Courtyard Phase I. Real notes from real buyers beat any brochure.

Start a discussion