PERFECT RESIDENCYMahaRERA P51600002318

by PERFECT DEVELOPERS

807/3B/33/34, Nashik, 422005

Sept 2019
Possession
67.3%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Sept 2019) has passed with construction at 67.3%.

Official RERA facts

Registration
P51600002318
Status
Ongoing
Stage
Certificate Signed
Possession
September 2019
Construction
67.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drains20%
Landscaping & Tree Planting60%
Water conservation /Rain water harvesting30%
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2017
Floors
8

Buyer community

Connect with other buyers and owners of PERFECT RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PERFECT RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.