Under construction

Nishant iken Phase 1MahaRERA P51600004851

by Ganesh kashiram ahire

1084/2, Nashik (M Corp.), 422003

Jun 2019
Possession
76.1%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2019) has passed with construction at 76.1%.
  • Promised amenities not started. Kids Play Area, Sports / Jogging are at 0% build with possession due Jun 2019 per the RERA filing.

Official RERA facts

Registration
P51600004851
Status
Ongoing
Stage
Certificate Signed
Possession
June 2019
Construction
76.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths20%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)10%
Storm Water Drainsnot started
Landscaping & Tree Planting10%
Street Lighting20%
Community Buildings80%
Water conservation /Rain water harvesting10%
Fire protection and fire safety requirements20%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Space50%
Children Play Areanot started
Multipurpose Courtnot started

Building & registration

RERA registered
Aug 2017
Floors
8

Buyer community

Connect with other buyers and owners of Nishant iken Phase 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Nishant iken Phase 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.