Under construction

RiveraMahaRERA P51600004983

by Renuka Constructions

Plot No. 15, S.No.56/1, Bendkule Nagar, 422013

Dec 2020
Possession
88.6%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 88.6%.

Official RERA facts

Registration
P51600004983
Status
Ongoing
Stage
Certificate Signed
Possession
December 2020
Construction
88.6% complete
Units sold
0 of 0

RERA complaint record1 record

  • ComplaintCC0010000000000747 Sept 2018
    VIJAY KUMAR MAHABIRPRASAD JATIA vs RENUKA CONSTRUCTION
    74.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildings75%
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone
Podium Slabdone

Building & registration

RERA registered
Aug 2017
Floors
11

Buyer community

Connect with other buyers and owners of Rivera โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Rivera. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.