PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ASHOK RESIDENCYMahaRERA P51600006162

by Jitu Ashok Pawar

PLOT NO 44 AND 45, S. NO. 191/1A, Nashik, 422007

Oct 2020
Possession
72.3%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 72.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2020 per the RERA filing.

Official RERA facts

Registration
P51600006162
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally December 2018
Construction
72.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply95%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of ASHOK RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.