Under construction

SHREE SAI RESIDENCYMahaRERA P51600009143

by SHREE SAI CONSTRUCTIONS

SR NO 308/A/67 PLOT NO 67, Nashik (M Corp.), 422010

Sept 2018
Possession
58.6%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Sept 2018) has passed with construction at 58.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2018 per the RERA filing.

Official RERA facts

Registration
P51600009143
Status
Ongoing
Stage
Certificate Signed
Possession
September 2018
Construction
58.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply25%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvesting90%
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of SHREE SAI RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHREE SAI RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.