SPRINGFIELDMahaRERA P51600011544

by VASUNDHARA CONSTRUCTION

PLOT NO 53 54, Nashik, 422009

Jul 2018
Possession
51.8%
Built
2
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jul 2018) has passed with construction at 51.8%.

Official RERA facts

Registration
P51600011544
Status
Ongoing
Stage
Certificate Signed
Possession
July 2018
Construction
51.8% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of SPRINGFIELD โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SPRINGFIELD. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.