VIJAYSHRUSHTIMahaRERA P51600011620

by JAY DEVELOPERS

228/1B, Nashik (M Corp.), 422008

Jun 2023
Possession
86.4%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2018, now proposed Jun 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 86.4%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Jun 2023 per the RERA filing.

Official RERA facts

Registration
P51600011620
Status
Ongoing
Stage
Certificate Signed
Possession
June 2023originally December 2018
Construction
86.4% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Community Buildingsnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
10

Buyer community

Connect with other buyers and owners of VIJAYSHRUSHTI โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VIJAYSHRUSHTI. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.