Under construction

SHAANTAI APARTMENTMahaRERA P51600011945

by MAYURESH CONSTRUCTIONS OPC PRIVATE LIMITED

5P/11/1/3/16/A, Nashik (M Corp.), 422013

Jul 2022
Possession
65.5%
Built
0
Complaints
12
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2019, now proposed Jul 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2022) has passed with construction at 65.5%.

Official RERA facts

Registration
P51600011945
Status
Ongoing
Stage
Certificate Signed
Possession
July 2022originally December 2019
Construction
65.5% complete
Units sold
6 of 12

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvesting50%

Building & registration

RERA registered
Sept 2017
Floors
5
Unit mix
12 res ยท 0 comm
Architect
Ar Abhijeet Malpure

Buyer community

Connect with other buyers and owners of SHAANTAI APARTMENT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHAANTAI APARTMENT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.