NANDAN CARNIVAL A BUILDINGMahaRERA P51600012372

by NANDAN BUILDCON PVT LTD

GAT NO 39 TO 49, ADGAON, 422003

Mar 2028
Possession
57.1%
Built
0
Complaints
104
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Dec 2019, now proposed Mar 2028 per the RERA filing.
Ghatkopar / VikhroliUpper-mid

Metro-1 anchor with Godrej's Vikhroli land bank next door.

Growth drivers:
Metro 1 interchange, Eastern Express Highway, corporate campuses.
Who buys here:
Families wanting east-side connectivity to BKC/Fort.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P51600012372
Status
Ongoing
Stage
Certificate Signed
Possession
March 2028originally December 2019
Construction
57.1% complete
Units sold
7 of 104

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths25%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drains20%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposal70%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements30%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Space60%

Building & registration

RERA registered
Sept 2017
Floors
15
Unit mix
104 res ยท 0 comm
Architect
DISIGN SQUARE ASSOCIATES

Buyer community

Connect with other buyers and owners of NANDAN CARNIVAL A BUILDING โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NANDAN CARNIVAL A BUILDING. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.