Under construction

AARKAY BLOSSOMMahaRERA P51600015371

by MAITRA BUILDTECH PRIVATE LIMITED

SR NO. 82/1A, 31/32/33, PANCHAVATI, 422003

Jan 2022
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jan 2022) has passed with construction at 90.9%.

Official RERA facts

Registration
P51600015371
Status
New
Stage
Certificate Signed
Possession
January 2022
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Landscaping & Tree Planting50%
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%
Open Parking50%

Building & registration

RERA registered
Feb 2018
Floors
8

Buyer community

Connect with other buyers and owners of AARKAY BLOSSOM โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AARKAY BLOSSOM. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.