Under construction

HARI OM PLAZAMahaRERA P51600017812

by SAMARTH BUILDCON

PLOT NO 3 AND 4 S NO 855 1144 1 TO 3/4 AND 1 TO 3/4/4, SINNAR, 422103

Dec 2027
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P51600017812
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2023
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Sept 2018
Floors
6

Buyer community

Connect with other buyers and owners of HARI OM PLAZA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching HARI OM PLAZA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.