Under construction

NIRMANS MANGALUMMahaRERA P51600018587

by NIRMAN ESTATE DEVELOPERS PVT LTD

S NO 27/1/5, S NO 25/1/2, BEHIND GURUJI RUGNALAYA, OFF GANGAPUR ROAD, 422013

Dec 2022
Possession
78.2%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 78.2%.
  • Promised amenities not started. Gymnasium, Landscaped Garden, Kids Play Area are at 0% build with possession due Dec 2022 per the RERA filing.

Official RERA facts

Registration
P51600018587
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
78.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Aggregate area of recreational Open Spacenot started
Open Parking17%
CCTV CAMERA FOR ENTRANCE EXIT AND TERRACEnot started
GYM ZONE CONSISTING OF CARDIO MULTI STATION GYM AND OPEN GYMnot started
KIDS PLAY EQUIPMENTS LUDO AND SNAKES AND LADDER GAMEnot started
SMALL STAGE AND PARTY AREA ON TERRACEnot started
YOGA AND MEDITATATION ENCLOSURE AND SKY LOUNGE ON TERRACEnot started
CAROM CHESS AND TABLE TENNIS ENCLOSUREnot started
POWER BACK UP FOR LIFT AND COMMON AREASnot started

Building & registration

RERA registered
Nov 2018
Floors
7

Buyer community

Connect with other buyers and owners of NIRMANS MANGALUM โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NIRMANS MANGALUM. Real notes from real buyers beat any brochure.