Possession
89.1%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 89.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.

Official RERA facts

Registration
P51600020657
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
89.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lighting50%
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting50%
Energy managemcnt50%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Space60%

Building & registration

RERA registered
Apr 2019
Floors
9

Buyer community

Connect with other buyers and owners of Samraat Apna Ghar Phase-II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Samraat Apna Ghar Phase-II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.