PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SADGURU HOMESMahaRERA P51600022296

by SHREE SADGURU HOMES

2/4/5/6 SNO 188/2A 1J/1 D1J/1T, HIRAWADI, 422003

Dec 2028
Possession
69.3%
Built
0
Complaints
265
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Mar 2026, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P51600022296
Status
New
Stage
Certificate Signed
Possession
December 2028originally March 2026
Construction
69.3% complete
Units sold
121 of 265

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirements20%
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2019
Floors
19
Unit mix
247 res ยท 18 comm
Architect
KIRAN MOGHE

Buyer community

Connect with other buyers and owners of SADGURU HOMES โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SADGURU HOMES. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.