SHREENAVSHAKTI APARTMENTMahaRERA P51600022623

by SWAMI CONSTRUCTIONS

S NO 507 F P NO 31 PLOT NO 15 16, BHABHA NAGAR MUMBAI NAKA, 422011

Sept 2022
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 90.9%.

Official RERA facts

Registration
P51600022623
Status
New
Stage
Certificate Signed
Possession
September 2022
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Oct 2019
Floors
6

Buyer community

Connect with other buyers and owners of SHREENAVSHAKTI APARTMENT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHREENAVSHAKTI APARTMENT. Real notes from real buyers beat any brochure.