Under construction

BUSINESS PLUSMahaRERA P51600024000

by MANGO ESTTATE

SURVEY No. 588/2, FINAL PLOT No. 115/P, CTS No. 7256, NEAR HOTEL SANDIP NASHIK, 422001

Dec 2026
Possession
90.2%
Built
0
Complaints
182
Units
High risk
  • Possession delayed ~1 yr. Originally promised Sept 2025, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51600024000
Status
New
Stage
Certificate Signed
Possession
December 2026originally September 2025
Construction
90.2% complete
Units sold
3 of 182

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply97%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lighting75%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Jan 2020
Floors
10
Unit mix
0 res ยท 182 comm
Architect
SUMIT M KUMATH M KUMATH

Buyer community

Connect with other buyers and owners of BUSINESS PLUS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BUSINESS PLUS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.