Under construction

GOLDEN BRICKSMahaRERA P51600025112

by SIDDHI BUIILDTECH

32/A/1, NASHIK ROAD, 422101

Dec 2026
Possession
90.9%
Built
0
Complaints
126
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51600025112
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
90.9% complete
Units sold
98 of 126

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Aggregate area of recreational Open Spacedone
Open Parkingnot started

Building & registration

RERA registered
Mar 2020
Floors
17
Unit mix
112 res ยท 14 comm
Architect
Prashant Themaskar

Buyer community

Connect with other buyers and owners of GOLDEN BRICKS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GOLDEN BRICKS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.