Under construction
THE EMPIREMahaRERA P51600025617
S.No. 646/7B/1/2/A2, CTS No. 6821 to 6824. F.P. No. 250, TPS-2, Tilakwadi, 422002
Jun 2026
Possession
77.3%
Built
0
Complaints
56
Units
Caution
- Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 77.3%.
Official RERA facts
- Registration
- P51600025617
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2026
- Construction
- 77.3% complete
- Units sold
- 19 of 56
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Street Lightingdone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone
Building & registration
- RERA registered
- Jul 2020
- Floors
- 23
- Unit mix
- 56 res ยท 0 comm
- Architect
- Kapadia Associates Design LLP
Buyer community
Connect with other buyers and owners of THE EMPIRE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching THE EMPIRE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.