PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

THE EMPIREMahaRERA P51600025617

by BHAVIK & SARAF VENTURES

S.No. 646/7B/1/2/A2, CTS No. 6821 to 6824. F.P. No. 250, TPS-2, Tilakwadi, 422002

Jun 2026
Possession
77.3%
Built
0
Complaints
56
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 77.3%.

Official RERA facts

Registration
P51600025617
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
77.3% complete
Units sold
19 of 56

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Street Lightingdone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Jul 2020
Floors
23
Unit mix
56 res ยท 0 comm
Architect
Kapadia Associates Design LLP

Buyer community

Connect with other buyers and owners of THE EMPIRE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching THE EMPIRE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.