Under construction

SAI RAJMahaRERA P51600026803

by Anil Shankar Aher

PLOT NO 44 SURVEY NO 647/20 OF NASHIK SHIWAR, RACCA GARDEN, 422002

Apr 2025
Possession
80.5%
Built
0
Complaints
12
Units
High risk
  • Possession date passed. The proposed possession date (Apr 2025) has passed with construction at 80.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2025 per the RERA filing.

Official RERA facts

Registration
P51600026803
Status
New
Stage
Certificate Signed
Possession
April 2025originally April 2024
Construction
80.5% complete
Units sold
6 of 12

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Oct 2020
Floors
6
Unit mix
12 res ยท 0 comm
Architect
AR. DHIRAJ WALUNJ

Buyer community

Connect with other buyers and owners of SAI RAJ โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI RAJ. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.