All RERA projects
๐๏ธ
Under construction
TULASI BAUGMahaRERA P51600027664
by RISHIKESH BUILDERS AND DEVELOPERS
survey no 195/5, deolali, 422101
Dec 2027
Possession
90.9%
Built
0
Complaints
84
Units
High risk
- Possession delayed ~4 yrs. Originally promised Jun 2024, now proposed Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P51600027664
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally June 2024
- Construction
- 90.9% complete
- Units sold
- 53 of 84
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Building & registration
- RERA registered
- Dec 2020
- Floors
- 9
- Unit mix
- 84 res ยท 0 comm
Buyer community
Connect with other buyers and owners of TULASI BAUG โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching TULASI BAUG. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.