BLUE LOTUSMahaRERA P51600029863

by KULSWAMINI ESTATES

PLOT NO 16, 18, 20,OF S NO. 793/1/2/2A TO 2E/794/1/794/3, GOVIND NAGAR, 422009

Mar 2024
Possession
84.5%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 84.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2024 per the RERA filing.

Official RERA facts

Registration
P51600029863
Status
New
Stage
Certificate Signed
Possession
March 2024
Construction
84.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
Jul 2021
Floors
8

Buyer community

Connect with other buyers and owners of BLUE LOTUS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BLUE LOTUS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.