Under construction

SAI COURTMahaRERA P51600029904

by JAY WIN DEVELOPERS

PLOT NO 3PLUS4PLUS10PLUS11PLUS12PLUS13 S NO388/1PLUS2/A/2/1, NASHIK, 422005

Dec 2026
Possession
89.1%
Built
0
Complaints
94
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P51600029904
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
89.1% complete
Units sold
13 of 94

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply10%
Sewerage (Chamber, Lines, Septic Tank , STP)10%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements10%
Open Parking10%

Building & registration

RERA registered
Jul 2021
Floors
12
Unit mix
88 res ยท 6 comm
Architect
HEMANT DUGAD

Buyer community

Connect with other buyers and owners of SAI COURT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI COURT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.