All RERA projects
๐๏ธ
Under construction
BELLA CASAMahaRERA P51600031153
733/2B/2/1/2,F.P.No-486P, KRUSHI NAGAR, 422005
Mar 2027
Possession
66.8%
Built
0
Complaints
28
Units
High risk
- Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Mar 2027 per the RERA filing.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P51600031153
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally March 2025
- Construction
- 66.8% complete
- Units sold
- 11 of 28
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvesting70%
Fire protection and fire safety requirements60%
Electrical meter room, sub-station, receiving station60%
Building & registration
- RERA registered
- Oct 2021
- Floors
- 25
- Unit mix
- 28 res ยท 0 comm
Buyer community
Connect with other buyers and owners of BELLA CASA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching BELLA CASA. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.