SAMRADNI PRESTIGEMahaRERA P51600031501

by ABHISHEK ANNASAHEB GADAKH

PLOT NO 14 AND 15 SURVEY NO 179 1,2 OF SINNAR NASHIK, SINNER NASHIK MAHARASHTRA, 422103

Mar 2027
Possession
81.8%
Built
0
Complaints
20
Units
Caution
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Mar 2027 per the RERA filing.

Official RERA facts

Registration
P51600031501
Status
New
Stage
Certificate Signed
Possession
March 2027originally December 2025
Construction
81.8% complete
Units sold
16 of 20

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Oct 2021
Floors
6
Unit mix
20 res ยท 0 comm
Architect
NISHANT MAHESHWARI

Buyer community

Connect with other buyers and owners of SAMRADNI PRESTIGE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAMRADNI PRESTIGE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.