PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

NEETI NIKETANMahaRERA P51600032403

by ROOPAYAN DEVELOPERS

PLOT NO 39-40 SURVEY NO. 62/1/62/2/63/64 CHANDSHI, NANDANVAN CHANDSHI, 422003

Dec 2026
Possession
90.9%
Built
0
Complaints
0
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P51600032403
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Street Lightingdone
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Jan 2022
Floors
8

Buyer community

Connect with other buyers and owners of NEETI NIKETAN โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NEETI NIKETAN. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.