Under construction

VAISHNAVI PLAZAMahaRERA P51600032657

by TRIMURTI CONSTRUCTION

Survey No. 505/1/1A/1/1/2/505/1/1A/2, Adgaon Shiwar, ADGOAN SHIVAR, 422003

Apr 2027
Possession
57.3%
Built
0
Complaints
0
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Apr 2024, now proposed Apr 2027 per the RERA filing.

Official RERA facts

Registration
P51600032657
Status
New
Stage
Certificate Signed
Possession
April 2027originally April 2024
Construction
57.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jan 2022
Floors
8

Buyer community

Connect with other buyers and owners of VAISHNAVI PLAZA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VAISHNAVI PLAZA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.