Laxmi Commercial ComplexMahaRERA P51600032710
P.NO. 20/2/1PLUS2 S.NO. 649A/1/11B/A PLUS B F.P.NO 331, RACCA COLONY, 422002
Dec 2027
Possession
65%
Built
0
Complaints
11
Units
Caution
- Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P51600032710
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2024
- Construction
- 65% complete
- Units sold
- 1 of 11
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Jan 2022
- Floors
- 10
- Unit mix
- 0 res ยท 11 comm
- Architect
- Ar Sumit Kumath
Buyer community
Connect with other buyers and owners of Laxmi Commercial Complex โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Laxmi Commercial Complex. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.